The American Air Force had, for years, disposed of munitions by exploding them on the beaches of Guam, near Chamorro cultural sites and the island’s coral reefs. The case asks two questions whose effect will reverberate beyond Guam, which are the following: can the respondents sue before a state or territorial regulator’s decision based on the Resource Conservation and Recovery Act of 1976 (RCRA) permit; and does the National Environmental Policy Act of 1969 (NEPA) review apply when there already has been an RCRA review?
The Resource Conservation and Recovery Act of 1976 is a federal law governing hazardous waste management. The act allows the administrator of the Environmental Protection Agency (EPA) to create “guidelines for solid waste management,” and establish a “permit program to regulate the treatment…of hazardous waste,” creating requirements for permit applications. The Administrative Procedure Act is a federal law that grants the courts, under judicial review, the ability to discard agency unlawful decisions. The catch is that the courts may only review final agency action, which is a decision that ends the decision-making process of an agency and has legal ramifications, as stated in Bennett v. Spear (1997). The first major question is whether the Air Force application permit process meets final agency action.
The National Environmental Policy Act of 1969 creates requirements for federal agencies to study the environmental impacts of policy actions before taking such actions, and requires them to create an Environmental Assessment or Environmental Impact Statement, looking at alternatives and having a public input period. This law only requires review of an environmental policy before going forward, not that a certain action must be taken for or against the policy.
The United States Air Force has held an RCRA permit since 1982 to dispose of and treat unexploded munitions at Andersen Air Force Base in Guam, and the Guam EPA has renewed the permit each time the Air Force asked for renewal. The Air Force detonates the munitions on Tarague Beach, which is 50 yards from the Pacific Ocean. Tarague Beach, however, sits on ancestral Chamorro land that was taken by the military from families after World War II. The beach is a historical and cultural site, and sits above Guam’s source of drinking water. Throughout the decades of detonation, the Air Force has never provided a NEPA Environmental Assessment or Environmental Impact Statement for the procedure.
In May 2021, the Air Force applied for a routine renewal of their RCRA permit, and the Guam EPA issued a draft permit and had a public comment period. It had not yet reached a final decision by 2022, when Prutehi Guahan, a grassroots group formerly known as Prutehi Litakyan, brought the suit, making the argument that the Air Force needed to conduct a NEPA review before their application. The district court granted the government’s motion to dismiss the suit, holding that there was no final agency action. The U.S. Court of Appeals for the Ninth Circuit reversed the lower court’s decision, ruling that the Air Force’s submission of the permit renewal application “imposes a legal obligation upon the agency” and the application met final agency action requirements. The government then petitioned for certiorari to the United States Supreme Court, which granted certiorari on March 9th, 2026. The court heard oral argument on October 7th, 2026, with Sopan Joshi, the Assistant to the Solicitor General, arguing on behalf of the petitioners and Caroline A. Flynn on behalf of the respondents, but the case is yet to be decided.
Does an application for a permit represent a final decision? Initially, it seems not to be, as an application is just a request that can be approved or denied. Justice Thomas made this view known during oral arguments, describing the action as “a regulated body’s decision to apply to a regulatory body.” In plain English, it is just a regulated party asking permission – permission that has not been granted nor denied. The petitioners, in response, contend that the Air Force was not acting as a federal regulator, but acting as a landowner in a "proprietary capacity.” Having that sort of framing, though, makes it unclear who is making the decisions. While the Guam EPA was deciding on whether or not to approve the permit, the Air Force decided on the plan of action, settling on open detonation at Tarague Beach without considering alternatives. Such a complete decision is the type that NEPA would require an agency to use to examine its policy before deciding to commit to it. At the same time, as Justice Kagan contends, since most federal projects are “subject to regulatory approvals,” not treating these actions as final would mean it would be difficult to conduct timely reviews. The best objection petitioners have is that of timing: why didn’t respondents wait until after the Guam EPA released its action so that it would be known what the permit would look like? There are tradeoffs to waiting, which petitioners mention. In the case that a later court required full NEPA review of the permitting process, the process would restart and years of permitting work would be wasted. It could be, as Justice Sotomayor describes it, literally “inviting litigation to unravel perhaps years of work.” The concern is that if NEPA is to apply, the time to say so is before permit action, not after it.
If the suit is allowed to go forward on the final action question, the more substantive question is whether NEPA applies or not. Petitioners hold that the RCRA permitting process – with its draft permit and public comment period – removed the NEPA obligation, and that because the RCRA permits were continually renewed, the Air Force had no such obligation to follow an additional procedure. Especially since the Air Force has never had to provide an Environmental Impact Statement or Environmental Assessment since 1982 for any RCRA renewal, that would imply that NEPA was not needed as an extra process. Justice Kavanaugh described requiring both as creating a “great uncertainty… of two processes back to back,” which would be “the least sensible of all options on the table.”
Redundancy is not a legal argument, however; it is a practical one. Congress had written NEPA exemptions into statute for other laws when they did not want agencies to go through the extra step; no exception was made for RCRA. Without the “express exclusion” authorized by Congress or a “clear and fundamental conflict” with NEPA, ordinary policy is that “if you can do both, you need to do both,” which both Justices Jackson and Gorsuch mentioned. The two permits also seem to cover different processes: while the RCRA deals with hazardous waste and whether it meets regulatory standards, NEPA asks the deeper questions of whether other sites or methods of destruction, or even the land’s cultural importance, were considered. Guam’s EPA is responding to what the Air Force plan is, not what it is not.
I personally believe the Court will rule in favor of petitioners, chiefly by ruling that the application for a permit is not final agency action. This would allow the Court to avoid the more difficult question of NEPA’s application, allowing for potentially further litigation by Prutehi Guahan once Guam’s EPA releases the permit. While it is true that the Court seems wary of altering how the permitting process works, the fact that there is only an interim permit likely leads them to require a final permit before any ruling on the merits of NEPA. Regardless of what the Court ends up deciding, this case will be highly influential in the question of whether NEPA, a cornerstone of environmental policy, truly remains the cornerstone of environmental law or becomes subordinate to narrower laws.